Mills Contracts Ltd, were contracted on behalf of Omexom Ireland & Renewables to complete the construction of the contestable grid connection of Evishagaran Wind Farm to the new NIE Agivey 110kV cluster substation. The scope of supply of the ICP Contractor was the civil and electrical works required for a double 33kV underground cable circuit (duplex configuration). The approximate total cable route length between the Evishagaran 33kV site substation and the proposed location of the Agivey 110kV cluster substation is 6.75 km. To construct this underground cable grid connection contestably, Mills Contracts Ltd needed to be Lloyds accredited as Independent Connection Provider (ICP) as per NIE Functional Specification Guidelines
Works included within the contract were:
The provision of Excavation, Cable Laying & Reinstatement Works associated with: